Get a Septic Permit in Sevier County: Easy Guide

How to Obtain a Septic Permit in Sevier County: A Step-by-Step Guide
Why You Need a Septic Permit in Sevier County
Step 1: Plat Approval for Subdivision Lots
-
Soil Evaluation: A soil scientist examines the lot to ensure it can handle septic waste.
-
Bedroom Limit: The evaluation sets the maximum number of bedrooms allowed, based on the lot’s capacity.
-
If your property isn’t in a subdivision, you can skip this step and move to the permit application. You may still need the services of a soil scientist if required by the county.
Step 2: Applying for Your Septic Permit in Sevier County
How to Apply for a Septic Permit
-
Complete the Application: Download and fill out the one-page septic permit application form available from the Sevier County Department of Environmental Health.
-
Survey and Staking: Hire a surveyor to mark your lot’s corners clearly. Stake out the exact location of your house so the environmental engineer can assess the site accurately.
-
Soil Mapping (If Needed): In some cases, soil mapping by a qualified soil scientist may be required. Contact a local soil scientist in Sevier County if necessary.
-
Submit Documentation: Provide all required documents, including the application, survey, and site plans, to the Sevier County Department of Environmental Health at 227 Cedar Street, Sevierville, TN 37862. The environmental engineer will review your submission for compliance.
-
Receive Your Permit: Once approved, you’ll receive your septic permit, valid for three years, specifying the number of bedrooms allowed based on your lot’s capacity.
Tips for a Smooth Application Process
-
Double-check that all documentation is complete to avoid delays.
-
Call the Sevier County Department of Environmental Health at (865) 429-1766 if you’re unsure about soil mapping requirements.
-
Work with a licensed surveyor to ensure accurate staking and site plans.
Step 3: Septic System Installation and Final Approval
-
Installation: Your builder will install the septic system per the permit specifications, including the tank, drain field, and other components.
-
Inspection: The system must remain uncovered until an environmental engineer inspects it. Schedule this inspection by calling (865) 429-1766.
-
Approval and Covering: If the system passes inspection, you’ll receive a septic approval. Your builder can then cover the system and connect it to your home’s plumbing.
-
Ready for Use: Once connected, your septic system is fully operational and ready to support your new home.
Ensuring Compliance During Installation
-
Follow the permit specifications exactly to avoid failing the inspection.
-
Schedule the inspection promptly to keep your project on track.
-
Address any issues flagged during the inspection before covering the system.
Explore Sevier County While Building Your Home
Conclusion

Categories
Recent Posts









GET MORE INFORMATION

EXIT Tennessee Realty Pros
License ID: 261589 Tennessee
License ID: 261589 Tennessee